[Feb. 25, 2008]
Electrical Upgrade - Phase II
The electrical project began late September 2007 and is scheduled for completion by the end of 2008. The construction area is fenced-off on the southwest side of Willis Hall. Please contact Kirk Campbell at x4460 if you have any questions. [Posted Oct. 1, 2007]
Week of May 12: A large opening on the top of the vault will be used to crane-lift transformers and switch gear into the vault. The opening will be accessed periodically for large steel conduit and heavy electrical cable until August.
Electrical shutdowns: Future individual building shutdowns and an all-campus shutdown are in the planning stages as we work through campus events and schedules. These dates and their effects will be published as they are scheduled.
Mid-August: After the all-campus shutdown and switch-over in mid-August, the vault will be capped and the area filled and graded to sod which should be completed by the end of August.
Text Only/ Printer-Friendly
|
-
What to do in case of an emergency
-
Forms: Facilities Work Request, Facility Change Request, and Set Up Request Forms
-
Director of Facilities, Facilities Supervisors, Custodial Staff, Employee Housing Coordinator, Grounds Staff, Interior Design, Maintenance Staff, Energy Management, and Project Managers
-
Director of Facilities, Custodial, Employee Housing, Grounds, Interior Design, Maintenance, Energy Managment, Project Management, and Set Up Services
-
Index of Campus Buildings, Historical Building Information, Council Ring Information, Campus Maps, Service Vehicle Parking Map
-
Campus Project Notices and Fiscal Year Budget Projects
-
See the Campus Plan developed by Civitas
-
See the complete survey report
-
Safety Glasses Information and Prescription Form
-
Campus storage policy, furniture policy, moving services policy, painting policy, animal/pet policy, student storage policy, and work request policy.
-
Facilities Management is responsible for managing the College's annual energy budget and the electrical and steam distribution infrastructure required to light, heat, and cool the campus.
-
Indoor Air Quality and Mold Information, Campus Radon Testing, and Carleton's Water Report
-
Carleton rolled out a new recycling and composting program in its efforts to be committed to environmentally-friendly practices, coinciding with the beginning of the 2007-08 academic calendar on Monday, Sept. 10.
-
Environmental Statement, Sustainable Efforts at Carleton College, the History of Carleton's Wind Turbine, Frequently Asked Questions About the Wind Turbine, and Green Roofs and Other ENTS Student Projects.
-
Student Employment Applications and Information
|