Construction Schedule
Proposed schedule for construction of the new residence halls:
| East Building | ||
| Activity | Beginning | Ending |
| Building Structure | Beginning of August | End of December |
| Exterior Skin (Windows, Brick, Stucco) | Beginning of December | Mid May |
| Clay Roof Tile | Middle of March | End of May |
| Interior Rough-Ins | Mid January | Mid April |
| Interior Finishes | Beginning of March | End of July |
| Furniture Move In | Beginning of August | End of August |
| West Building | ||
| Activity | Beginning | Ending |
| Building Structure | Mid September | End of January |
| Exterior Skin (Windows, Brick, Stucco) | Beginning of January | Beginning of June |
| Clay Roof Tile | End of March | End of May |
| Interior Rough-Ins | Beginning of March | Mid May |
| Interior Finishes | Mid April | End of July |
| Furniture Move In | Beginning of August | End of August |