Construction Schedule

Proposed schedule for construction of the new residence halls:

Cassat Hall  (East Building)    
Activity Beginning Ending
Building Structure Beginning of August End of December
Exterior Skin (Windows, Brick, Stucco) Beginning of December Mid May
Clay Roof Tile Middle of March End of May
Interior Rough-Ins Mid January Mid April
Interior Finishes Beginning of March End of July
Furniture Move In Beginning of August End of August
     
Memorial Hall (West Building)    
Activity Beginning Ending
Building Structure Mid September End of January
Exterior Skin (Windows, Brick, Stucco) Beginning of January Beginning of June
Clay Roof Tile End of March End of May
Interior Rough-Ins Beginning of March Mid May
Interior Finishes Mid April End of July
Furniture Move In Beginning of August End of August