Week 17: Mini Bald Spot Drilling Complete

Wednesday, October 4, 2017

A cheer went up across the Mini Bald Spot at 7pm on Tuesday evening as drillers completed bore hole #77, the last hole on the field. While drilling is complete, the individual bores still have to be connected to each other and main lines running to and from the field. Trenches are currently being dug for this purpose, exposing the glacial till that covers the Mini Bald Spot. Once the connecting lines are in and the trenches are filled, the area will be turned over to maintenance for landscaping.